Capital Plan

North Shore Alerts
March 22, 2022 – MLFD – Fire hydrants replacements update
March 14, 2022 – Street Sweeping Tuesday March 15, 2022
March 11, 2022 – MLFD – Fire hydrant replacements
March 11, 2022 – Message from Bancker Construction and MLWD RE: Fire Hydrants
February 8, 2022 – NatGrid – Update on Gas Main work – New Information
January 31, 2022 – NatGrid – No work on Gas Mains Today
January 26, 2022 – NatGrid – Status & Where do we go from here
January 19, 2022 – NatGrid – Day 1
January 18, 2022 – National Grid Excavation Work Begins Wednesday, January 19
January 13, 2022 – Capital Plan – Further Details – CORRECTION
January 13, 2022 – Capital Plan – Further Details 
January 12, 2022 – Gas Main Project Begins 
January 11, 2022 – Letter to Residents – “New Starting Line” – “More Work With Less Money”

New Starting Line – “More Work with Less Money

Historical Context – In 2011, we hired the Village Engineer to do an evaluation of the condition of our roads ranking them 1 – 10. From this ranking and the survey details (linear and square footage), the Village developed our $1.1+ million, 10-Year Capital Plan; over 3 times our annual tax levy. We have been operating under, and saving to fund, that plan as follows:
– 2012 – $265,000 (24%); Extensive roadwork, on Bay Driveway and Bayview Circle,
– 2018 – $360,000 (32%); Extensive roadwork, on Waterway, Neck and Cove,
– 2021 – $343,000 (30%) Plan extensive roadwork in Bournedales and finally,
– 2023 – $157,000 (14%) Plan extensive roadwork on Shore and Beachway.
…………..$1,125,000

Current Situation –  The need for NatGrid to install new gas mains has disrupted our plans such that:
– The 2021 roadwork on the Bournedales has been delayed to 2022 to allow for the gas main to be replaced,
– The 2018 roadwork on Waterway, Neck and Cove has to be partially or fully redone due to gas mains,
– The 2023 roadwork on Shore and Beachway will be accelerated to 2022 for economies of scale

Resulting Scope of Work – The scope of work that results from the current situation is:
Required work –
…… – Paving Bournedales, + half road on Waterway, Neck, Cove and Beachway
Elective work
…… – Paving, curb-to-curb, on Waterway, Neck, Cove and Beachway,
…… – Paving Shore in 2022 instead of 2023,
…… – Replace various broken curbs, and various worn-out swales
…… – Replace entrance to Plandome Court North
…… – Stormwater management improvement on Waterway at Cove
…… – Repairs on Grandview, Bay Driveway, elsewhere
All information on construction plans and schedules is tentative and subject to change.

Projected Cost and Funding; Effect on Property Taxes – The projected cost of the project is approximately $600,000 (1.75 times our annual tax levy). Available funding includes (i) NYS Road Grants, (ii) NatGrid “half-road” road restoration funding, (iii) recently received COVID-19 funding (partially available), (iv) Consolidated Highway Improvement Program (“CHIPs”) funding and (v) Village Treasury. There will be no increase in your property taxes to do this work; all funding is in place.
All information (except not increasing your taxes for this work) is tentative and subject to change.

Project timeline (subject to change) – The timeline for the work is as follows:
– Done – Waterway/Neck gas mains
– January 2022 – NatGrid starts gas mains for Bournedales, Cove, Beachway
– March and April 2022 – Village various concrete and other work
– Mid April – NatGrid completes gas main work on Boournedale, Cove and Beachway
– May – June – Village paves Bournedales, Waterway, Neck, Cove,, Shore and Beachway
All information on construction plans and schedules is tentative and subject to change.

Graphic Rendering and Pictures of Paving Work
Map of Roadwork
Milling operations 2018
Paving operations 2018

National Grid Workplans (Note: not to scale)
The Waterway/Neck
Cove and Beachway
The Bournedales

Pictures and Renderings
Curbs and Swales:
.. >
Curbs
.. > Curb Repair 2022
.. > Swales
. > Swale Repair 2022
Plandome Court North Entrance:
.. > Eliminate broken concrete at Plandome Court North, Conform to clean look at Plandome Court South
Stormwater Management:
.. > Storm Drains at cross section between Waterway and Cove Drive
Concrete Road Repairs:
.. > Grandview Circle
Other repairs:
.. > Bay Driveway

Manhasset Lakeville Water Department Communications:
March 11, 2022 – MLFD – Fire hydrant replacements
Message from Bancker Construction and MLWD RE: Fire Hydrants
Fire Hydrant Locations
MLFD/Thornton Home – Pictures

National Grid Resident Communications
National Grid – December 30, 2021 Letter to Homeowners (with contact information)
National Grid – January 13, 2022 Banker Construction Letter to Residents

Frequently Asked Questions
FAQ
National Grid FAQ

Did we miss anything? Help us include common inquires.

Information on this website about construction plans and timing is subject to change